Work backward from the due dateβ€”when must each component be ordered?

πŸ“¦ Current Order
Loading...
Quantity 100 units
Assembly Time 2 weeks
Due Date Week 10
πŸ“‹ Bill of Materials

Drag components to the timeline β†’

πŸ† Score
0
Round 1 of 5
πŸ’‘ MRP Logic
βͺ Work backward from the due date
⏱️ Lead time = weeks before you need it
πŸ”— Child parts must arrive before parent assembly starts
Practice Operations: When you order materials in Module 2-3, you're doing MRP thinkingβ€”materials must arrive before production can start!
πŸ“… Schedule Components
Drop zone
Order placed
Assembly time
Due date
πŸ“š The MRP Question

MRP answers: "When should I order each component?"

If the finished product is due in Week 10 and takes 2 weeks to assemble, assembly must start by Week 8.

If a component has 3-week lead time, it must be ordered by Week 5 to arrive by Week 8.

Order Week = Need Week βˆ’ Lead Time