Scheduling Slots

Different sequences = different outcomes. Find the best order!

🎯 Challenge Round 1/5

Minimize Total Lateness β€” arrange jobs to reduce the total days late across all jobs.

πŸ“‹ Jobs to Schedule
Drag jobs into sequence (left = first, right = last):
πŸ“Š Schedule Results
Avg Flow Time
β€”
Total Lateness
β€”
Jobs Late
β€”
Max Lateness
β€”
Visual Schedule:
Add jobs to see the schedule
Score
0
Best sequences = more points!
πŸ“š Priority Rules
FCFS
First Come, First Served β€” process in arrival order
SPT
Shortest Processing Time β€” quickest jobs first (minimizes avg flow time)
EDD
Earliest Due Date β€” most urgent jobs first (minimizes max lateness)
CR
Critical Ratio β€” (time remaining)/(work remaining). Lowest first.
πŸ’‘ Key Insight

No single rule is "best" for everything. SPT minimizes average wait time, but EDD prevents any single job from being extremely late.

Practice Operations: In Module 1, you set job priorities 1-6. This is exactly the same decisionβ€”which order completes first affects when everything else finishes!