Dependency Detective

Investigate the relationships between activities

Your Mission

  • Read each project scenario carefully
  • Identify the correct dependency relationship
  • Consider what must happen before what can start
  • Think about real-world logic and constraints
Finish-to-Start (FS)
A must finish before B starts
Start-to-Start (SS)
A must start before B can start
Finish-to-Finish (FF)
A must finish before B can finish
Start-to-Finish (SF)
A must start before B can finish
🏆

Case Closed!

You've completed the investigation

Correct
0/10
Accuracy
0%
Score
0
🔍

Dependency Detective

Chapter 4 • Precedence Relationships

Case
1
Score
0
Streak
0
Loading case...
Company
CASE #1
📋 Case Brief
Loading scenario...
?
What is the dependency relationship?
💡 Explanation
The correct answer is...
1 of 10