PROJECT CRASHER

Shorten the project. Minimize the cost.

Your Mission

  • The project is behind schedule — you must hit the deadline
  • Click activities to "crash" them (pay extra to reduce time)
  • Only crash activities on the critical path
  • Find the cheapest way to meet the deadline
  • Crashing non-critical activities wastes money!
🏆

DEADLINE MET!

You shortened the project successfully

Final Duration
0 weeks
Total Spent
$0
Score
0
OPTIMAL SOLUTION
Step 1: Crash Activity X by 1 week ($500)
💰

PROJECT CRASHER

Chapter 4 • Cost-Time Tradeoffs

Level
1
Score
0
LEVEL 1
Loading...
Company
Target Deadline
10 weeks
Current Duration
12 weeks
PROJECT NETWORK Critical Path: A → B → C
CRASH BUDGET $5,000
Spent: $0
SELECTED ACTIVITY
Click an activity on the network to crash it
A
Design Phase
ON CRITICAL PATH
Normal Time
5 wks
Current Time
5 wks
Crash Limit
3 wks
Cost/Week
$500
Crash by: 0 weeks
Cost: $0 Saves: 0 weeks
⚠️ Not on critical path — this won't reduce project duration!
CRASH SUMMARY
Original Duration 12 weeks
Time Saved 0 weeks
Weeks Over Deadline 2 weeks
Total Crash Cost $0